OFFICE OF THE

SUPERINTENDING ENGINEER

M.P.P.KV.V .CO.LTD Satai Road, Chhatarpur

Construction of new 33/11 KV Substation alongwith its associate 33KV and 11KV line:

  • Supply, Installation, Testing & Commisioning of 2 x 5MVA, 33 / 11KV S / s 2 Nos.including Civil work, at Dhadari & Hatwaha a) 33 KV line : 11.82 KM b) 11 KV line : 3.90 KM
  • Supply, Installation , Testing & Commisioning of 3 x 3.15MVA, 33 / 11KV S / s 3Nos, including Civil work, at Lugasi, Vikrampur & Darguwah c) 33 KV Line : 51.90 KM d) 11 KV Line 7.20 KM

INITIATION DATE
16-05-2007

COMPLETION DATE
20-3-2009

WORK STATUS
Complete

Office of the

Dy. Chief Electrical Engineer (Works)

East side of HBJ Rly. Stn. , Construction Office Complex,Habibgan j,Bhopal

Modification/shifting of over head 33kv Powerline crossing by providing under ground HT XLPE cable between Tikamgarh-Chhatarpur Section of new B.G.Line

  1. 33KV 300 Sqmmx3 Core HT XIpe cable laying : 830 mtr
  2. 11KV 185 Sqmmx3 Core HT Xlpe cable laying : 1818 mtr

Total 2648 mtr 1. Jointing Kit 33KV : 15 Nos. 2. Jointing Kit 11KV : 32 Nos.

AMOUNT
Rs. 435,0557

INITIATION DATE
06-06-2008

COMPLETION DATE
20-12-2008

WORK STATUS
Complete

OFFICE OF THE

Dy. Chief Electrical Engineer

Opp. Divisional Training Centre, Khajanchi Bagh East Rly.Colony, Bhopal

Power Supply arrangement by separate 11kV feeder from MPSEB substation to Chhanera Railway station alongwith one VCB of Bhopal Division of WC Railway.

Extensionof 11 KV line on H-beam 152×152 mm 37-1 kg/Mtr. 11 mtrs long with AAAC Rabbit conductor as per Railway technical data . Supply & fixing of 11KV feeder control VCB, 200A with CT’s.

AMOUNT
Rs. 987,736

INITIATION DATE
20-06-2008

COMPLETION DATE

25-01-2019

WORK STATUS
Complete

OFFICE OF THE

Dy. Chief Electrical Engineer

Construction Office Complex, Habibganj, Bhopal

Modification/shifting of over head 33kv Power Line crossing by providing underground HT XLPE cable between Tikamgarh-Chhatarpur Section of new B.G.Line.

  • 11KV 185 SammX3 Core HT Xlpe cable laying : 5374 mtr.
  • 33KV 300 Sommx3 Core HT Yipe Cable Laying : 1764 m

Total 7438 mtr 1. Jointing Kit 11KV : 44 Nos 2. Jointing Kit 33KV : 18 Nos.

AMOUNT
Rs. 5332,098

INITIATION DATE
17-07-2008

COMPLETION DATE
20-12-2010

WORK STATUS
Complete

OFFICE OF THE

SUPERINTENDING ENGINEER

(Construction) Opp. Divisional Training Centre, Khajanchi Bagh East Railway Colony, Bhopal

Replacement of Overhead Power Line (ACSR Conductor) at Harda, Bina & Guna Station of Bhopal division of WC Railway.

Replacement of Overhead Power Line (ACSR Conductor) at Harda, Bina & Guna Station of Bhopal division of WC Railway.

AMOUNT
Rs. 113,0045

INITIATION DATE
12-12-2008

COMPLETION DATE
12-06-2019

WORK STATUS
Complete

OFFICE OF THE

Dy. Chief Electrical Engineer

(Construction) Opp. Divisional Training Centre, Khajanchi Bagh East Railway Colony, Bhopal

Supply , errection, commission of provision of Auxiliary Transformer in Connection with Interlocking of L.C Gates for Automatic Block Signalling and Power Lifting Barriers at Different L.C Gates Over Bhopal Division.

AMOUNT
Rs. 613,1615

INITIATION DATE
01-09-2009

COMPLETION DATE
30-03-2010

WORK STATUS
Complete

OFFICE OF THE

SUPERINTENDING ENGINEER

M.P.P.KV.V. CO. LTD Satai Road, Chhatarpur

Modification to OHE in connection with Construction of additional platforms no.6&7 at Itarsi station of Bhopal division

Modification to OHE in connection with Construction of additional platforms no.6&7 at Itarsi station of Bhopal division

AMOUNT
Rs. 323,4234

INITIATION DATE
10-11-2009

COMPLETION DATE
10-05-2010

WORK STATUS
Complete

OFFICE OF THE

ADDL. General Manager

MPMKVV CO.LTD. Bhopal

Turnkey basis the work of construction of shifting 33KV, 11KV, LT Line & 11 / 0.4KV Distribution Transformers Causing Obstruction in the proposed BRTS Corridor Route for Bhopal City Area from Habibganj underbridge to MPNagar Board Office Square.

  1. 33KV line : 4.5 KM
  2. 11KV line : 4.0 KM
  3. LT line : 0.5 KM
  4. Sub Station 11 / 04KV : 7 Nos.

AMOUNT
Rs. 10,482,960

INITIATION DATE
08-12-2009

COMPLETION DATE
15-01-2011

WORK STATUS
Complete

OFFICE OF THE

Chief Electrical Engineer

(Construction) IIIrd-floor, GM Building, Jabalpur

Electrification of staff quarters of Type – 1-72 units at JBP and Type – 1-50 units & Type – III – 6 units at JBP – Sub – Dn Railway stations along with Power supply arrangement at Jabalpur, WCR, JBP – Division.

Electrification of staff quarters of Type – 1-72 units at JBP and Type – 1-50 units & Type – III – 6 units at JBP – Sub – Dn Railway stations along with Power supply arrangement

AMOUNT
Rs. 4,064,760

INITIATION DATE
10-12-2009

COMPLETION DATE
09-06-2010

WORK STATUS
Complete

OFFICE OF THE

Dy. Chief Electrical Engineer

Jabalpur

Provision of 2 x 1000 kVA, 33/11kV substation at Burn complex , Jabalpur

Supply , errection , testing & commissioning of battery and 30V, 2.2V per cell , 100AH capacity lead acid battery with wooden stand duly painted with epoxy paint.

AMOUNT
Rs. 50,08,093

INITIATION DATE
16-12-2009

COMPLETION DATE
16-12-2010

WORK STATUS
Complete

OFFICE OF THE

ADDL. General Manager

MPMKVV CO.LTD.Bhopal

Turnkey basis of complete including laying of 33 KV line (Double Circuit) from newly proposed 100 KVA transformer at 220 KV S / S Chambal and Amrawad Khurd EHV 220 KV S / S for interconnection with existing 33 KV S / S Amrawad, Sidharth Lake City & Ballabh Nagar 33/11 KV S / S Route Length 8.85 Km.

complete including laying of 33 KV line (Double Circuit) from newly proposed 100 KVA transformer at 220 KV S / S Chambal and Amrawad Khurd EHV 220 KV S / S for interconnection with existing 33 KV S / S Amrawad, Sidharth Lake City & Ballabh Nagar 33/11 KV S / S Route Length 8.85 Km.

AMOUNT
Rs. 16,530,926

INITIATION DATE
20-01-2010

COMPLETION DATE
15-06-2011

WORK STATUS
Complete

OFFICE OF THE

Dy. Chief Electrical Engineer

(Construction) Opp. Divisional Training Centre, Khajanchi Bagh East Rly.Colony,Bhopal

Electrification of Station Building, Platform , Circulating Area And Power Supply Arrangements At Ratwas and Hinotiya-Pipalkheda Station In Bina-Guna Section Of Bhopal Division.

Power Supply Arrangement at Ratwas and Hinotia-Pipalkhera Station

AMOUNT
Rs. 27,52,216

INITIATION DATE
29-03-2010

COMPLETION DATE
29-09-2010

WORK STATUS
Complete

OFFICE OF THE

Chief Electrical Engineer

Jabalpur

Provision of Boring earth for 33/11kV Sub station at Burn Complex. Boring earth for 33/11kV Sub station at Burn Complex.

AMOUNT
Rs. 172,950

INITIATION DATE

29-11-2010

COMPLETION DATE
29-05-2011

WORK STATUS
Complete

OFFICE OF THE

Dy. Chief Electrical Engineer

East side of HBJ Rly. Stn. , Construction Office Complex, Habibganj, Bhopal.

Electrification of Station Building, Platform , FOB and power supply arrangement at Malkhedi station of JBP Division.
Power supply arrangement at Malkhedi station of JBP Divn.

AMOUNT
Rs. 27,96,289

INITIATION DATE
22-12-2010

COMPLETION DATE
22-06-2011

WORK STATUS
Complete

OFFICE OF THE

Chief Electrical Engineer

East side of HBJ Rly. Stn. , Construction Office Complex, Habibganj, Bhopal

Improvement to existing HT/LT power supply system at Bhopal & Habibganj on Bhopal Division of West Central Railway.

Improvement to existing HT/LT power supply system at Bhopal & Habibganj on Bhopal Division of West Central Railway

INITIATION DATE
13-06-2011

COMPLETION DATE
12-12-2011

WORK STATUS
Complete

OFFICE OF THE

Dy. Chief Electrical Engineer

East side of HBJ Rly. Stn. , Construction Office Complex, Habibganj, Bhopal

Rewiring of 855 nos. Different types old Railway Staff quarters ( Type-I , II , III, & IV and their equivalent), Cable laying work Over Head line work and provision of 1 no., 500 kVA, 33/0.415 kV Transformer at different stations over Bhopal Division.

AMOUNT
Rs. 17,941,434

INITIATION DATE
26-07-2011

COMPLETION DATE
25-05-2012

WORK STATUS
Complete

MADHYA PRADESH, BHOPAL

DEVELOPMENT CORPORATION LTD

Design , Supply , Erection , Installation , Testing & Commissioning of electrical Work at Network Monitoring Centre Building at Arera Hills,Bhopal.

  • 33kV Sub Station & 33kV line with 2 Nos.1600 KVA Dry Type Indoor Transformer
  • 33kV HT Panel / SF – 6 (2 incomer, 2 outgoing and 1 bus coupler)
  • DG Set 315kVA
  • Servo Stablizer 1600KVA
  • LT Control Main Panel, Control Panel & Bus Duct
  • Two Six Passenger Lift & One Goods Lifts

Two Six Passenger Lift & One Goods Lifts

AMOUNT
Rs. 64,750,531

INITIATION DATE
09-01-2012

COMPLETION DATE
30-12-2012

WORK STATUS
Complete

McNally

Bharat Engineering Company Limited.

Jabalpur

Supply & Erection, Testing And Commissioning of Electrical items of 6.6KV Overhead Transmission line for BOP Satpura TPS , MPPGCL Project ( BP02)

Supply & Erection, Testing And Commissioning of Electrical items of 6.6KV Overhead Transmission line for BOP Satpura TPS , MPPGCL Project ( BP02)

AMOUNT
Rs. 12,555,550

INITIATION DATE
27-01-2012

COMPLETION DATE
27-01-2013

WORK STATUS
Complete

M.P.PACHIM

KHETRA VIDYUT VITARAN CO.LTD.

Dewas, MP

33 KV independent feeder by laying an extension of 4.7 Kms . 33KV Double Circuit Line on 15 Mtrs.long . ” H ” Beam on behalf of M / s John Deere (I ) Ltd. The independent 33KV feeder is emanating from 220KV S / s Bhopal Road , Dewas for New HT Connection of 3900KVA on 33KV Double Circuit Line with digital summation of multiple feeders so as to achieve summated energy Apex metering system for HT Consumer along with laying of 3 core 400 sq.mm. XLPE underground Cable up to a route length of 300 mtrs . of each length . The 33KV Line emanating from M.P.P.T.C.L. 220KV Sub Station Dewas with independent 2 Nos . 33 KV Bay to the premises of John Deere ‘ s Tractor manufacturing plant at Village Khatamba , Dewas ( M.P ) against M.P.P.K.V.V.C.L.Dewas

The independent 33KV feeder is emanating from 220KV S / s Bhopal Road , Dewas for New HT Connection of 3900KVA on 33KV Double Circuit Line with digital summation of multiple feeders so as to achieve summated energy Apex metering system for HT Consumer along with laying of 3 core 400 sq.mm. XLPE underground Cable up to a route length of 300 mtrs . of each length . The 33KV Line emanating from M.P.P.T.C.L. 220KV Sub Station Dewas with independent 2 Nos . 33 KV Bay

AMOUNT
Rs. 10,157,994

INITIATION DATE
17-01-2013

COMPLETION DATE
15-03-2013

WORK STATUS
Complete

OFFICE OF THE

EXECUTIVE ENGINEER (ELECTRICAL)

M.P.HOUSING & INFRASTRUCTURE DEVELOPMENT BOARD,DIVISION ELECTRICAL INDORE (M.P)

External Electrification work at 23.35 Acres Land at Rau Indore

  •  Street Light Pole (Steel Tubular Polo) : 200 Nos.
  • Underground 11kV 3 core 300 sqmm & 240 sqmm Armored (XLPE) Cable : 1.483 KM & 1.757 KM.
  • Underground LT 3.5 core 300 sqmm & 150sqmm Armored (XLPE) Cable : 4.802 KM & 4.571 KM.
  • Underground LT 4 core 16 sqmm & 10 sqmm Armored (XLPE) Cable : 4.358 KM & 2.419 KM.
  • Packed Substation 315kVA copper wound outdoor unit with 2 Isolator + 1 SFU configuration with non walkin type. : 06 Nos.
  • Packed Substation 200KVA copper wound outdoor unit with 2 Isolator + 1 SFU configuration with non walkin type. : 01 Nos.
  • Feeder Pillar & earthing arrangements. : 56 Nos

AMOUNT
Rs. 35,435,470

INITIATION DATE

04-07-2013

COMPLETION DATE
29-11-2014

WORK STATUS
Complete